-
Requirements for installation work on Enectiva projects – automatic data collection from gauges
It is important to follow the instructions bellow while working on Enectiva installation projects. General If you are replacing a gauge or installing new one, then you have to fill the exchange protocol (which includes description of old and new gauge condition). It is necessary to write down the serial numbers of old and new gauges and M-bus module serial number too. After installation of any gauge or after mounting a digital output to the gauge or after installation of central unit you will …
-
Design of energy measurement systems in industrial sites
This manual serves as a standard for project architects and designers of energy measurement systems, who are using technologies working with M-Bus protocol. The aim of this standard is to provide a clear and transparent assignment of energy consumptions to technological units (heating, cooling, ventilation, production, lightning,…) or to economical units (renter, economic center,…). Another aim of this standard is to prepare a whole system of measurements for automatic data collection …
-
Inspection
When examining the area before installing the system for automatic data collecting it is necessary to provide at least these points: A list of all meters, that the client wants to be automatically captured. A scheme of the area with marked meters. It is necessary to estimate distance between the meters. Possible places where to put central units, which need to be powered with 230 V or 12V. Notes with accessibility to every place, installation difficulty, cabling management.